Select another date

Within the NSC Project at the construction site the following works are being performed:

- delivery of tertiary steel structures to the site;
- mounting of sliding system control module, inspection and assembling of equipment for the Arch sliding;
- Installation of MPFOP anchors of East End wall; 
- installation of sealing anchors at the north-east; 
- installation of special doors of the Arch; 
- installation of protective shielding of North garage and runways;
- installation completion of external and internal cladding. Progress - 99%;
- ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 98%;
- erection of the NSC ventilation stack was completed.

- Main Cranes System (MCS) installation:

* adjustment of crane-runway girders and rails;
* alignment and connection of control panels to the MCS, testing of control systems.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TB) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls from gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures.  Progress (construction part) - 99.6%.
* Electrical Equipment Building (EEB) – installation of fire alarm system and lighting within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures. Mounting of the frame metal structures for the EEB face heat insulation and lining.  
* Fire Units Access Lock – polishing, pre-coating, coating and painting of walls and ceilings inside the building. 
* Fire pump station (FPS) –installation of the southern fire water tank. Arrangement of face heat insulation and lining.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch end walls;
* Construction of roads in Local zone - 30%.

Erection of Arch western part steelwork:

Erected in total – 16,104.10 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

October 07, 2016
October 07, 2016
October 07, 2016
October 07, 2016
October 07, 2016
October 07, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- delivery of tertiary steel structures to the site;
- mounting of sliding system control module, inspection and assembling of equipment for the Arch sliding;
- Installation of MPFOP anchors of East End wall;
- installation of sealing anchors at the north-east;
- installation of special doors of the Arch;
- installation of protective shielding of North garage and runways;
- installation of external and internal cladding. Progress - 99%;
- ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 92%;
- erection of the NSC ventilation stack was completed.

- Main Cranes System (MCS) installation:

* adjustment of crane-runway girders and rails;
* alignment and connection of control panels to the MCS, testing of control systems.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TB) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls from gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures.  Progress (construction part) - 99.6%.
* Electrical Equipment Building (EEB) – installation of fire alarm system and lighting within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures. Mounting of the frame metal structures for the EEB face heat insulation and lining. 
* Fire Units Access Lock – polishing, pre-coating, coating and painting of walls and ceilings inside the building.
* Fire pump station (FPS) –installation of the southern fire water tank. Arrangement of face heat insulation and lining.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch end walls;
* Construction of roads in Local zone - 29%.

Erection of Arch western part steelwork:

Erected in total – 16,094.80 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

September 29, 2016
September 29, 2016
September 29, 2016
September 29, 2016
September 29, 2016
September 29, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- delivery of tertiary steel structures to the site;
- mounting of sliding system control module, inspection and assembling of equipment for the Arch sliding;
- Installation of MPFOP anchors of East End wall;
- installation of sealing anchors on ASRC roof;
- installation of special doors of the Arch;
- installation of protective shielding of North garage and runways;
- installation of external and internal cladding. Progress - 99%;
- ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 92%;
- the main part of the NSC ventilation stack was erected. The erection works are in progress.

- Main Cranes System (MCS) installation:

* the East and West bridges were moved to the Arch western half;
* Alignment and connection of control panels to MCS, training of personnel and testing of systems.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 98.56%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Fire Units Access Lock – polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors; installation of network systems inside the building.
* Fire pump station (FPS) – works on pre-coating, coating and painting of walls inside the building, installation of equipment; installation of the northern firewater tank is coming to an end, preparation for installation of the southern tank.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch end walls;
* Construction of roads in Local zone - 29%.

Erection of Arch western part steelwork:

Erected in total – 16,070.62 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

 

Select another date

Within the NSC Project at the construction site the following works are being performed:

- delivery of tertiary steel structures to the site;
- mounting of sliding system control module, inspection and assembling of equipment for the Arch sliding;
- Installation of MPFOP anchors of East End wall;
- installation of sealing anchors on ASRC roof;
- installation of special doors of the Arch;
- installation of protective shielding of North garage and runways;
- installation of external and internal cladding. Progress - 99%;
- ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 92%;
- the main part of the NSC ventilation stack was erected. The erection works are in progress.

- Main Cranes System (MCS) installation:

* the East and West bridges were moved to the Arch western half;
* Alignment and connection of control panels to MCS, training of personnel and testing of systems.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 98.4%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Fire Units Access Lock – polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors; installation of network systems inside the building.
* Fire pump station (FPS) – works on pre-coating, coating and painting of walls inside the building, installation of equipment; installation of the northern firewater tank is coming to an end, preparation for installation of the southern tank.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch end walls;
* Construction of roads in Local zone - 29%.

Erection of Arch western part steelwork:

Erected in total – 16,061.62 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

September 15, 2016
September 15, 2016
September 15, 2016
September 15, 2016
September 15, 2016
September 15, 2016

 

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of tertiary steel structures to the site;
- Mounting of sliding system control module, inspection and assembling of equipment for Arch sliding;
- Installation of anchors of East End wall;
- installation of sealing anchors on ASRU roof;
- installation of special doors of the Arch;
- installation of steel support structures of Ventilation stack;
- installation of protective shielding of North garage and runways;
- Installation of external and internal casing. Progress - 99%;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 91%;
- Welding of Arch Ventilation stack units. Pre-assembly of Ventilation stack maintenance sites.

- Main Cranes System (MCS) installation:

* Start of the procedure on moving MCS bridges to the Arch western half;
*
Alignment and connection of control panels to MCS, training of personnel and testing of systems.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 98%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Fire Subdivisions Access Lock (FSAL) – roof sealing, polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors;
* Fire pump station (FPS) – works relating to pre-coating, coating and painting of walls inside the building, installation of northern firewater tank;

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone - 28.2%.

Erection of Arch western part steelwork:

Erected in total – 16,045.01 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

September 08, 2016
September 08, 2016
September 08, 2016
September 08, 2016
September 08, 2016
September 08, 2016