NSC construction progress as of May 14, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- bolt tightening of West end wall structures;
- Lifting and installation of TP-4 tilting panel of Eastern end wall;
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clips, profiling of Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;

- Arrangement of technological building and auxiliary facilities:
   * Technological building (TB) – walling, roofing and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
   * Electrical device building – roofing (assembly of fittings and formwork);
   * Fire units acces airlock (wall reinforcement, installation of formwork, concreting and concrete curing).

- Arrangement of external and internal space of NSC (northern side):
   * Walls of hinged bearing gallery;
   * Storm and fire extinguishing water catchment basins;
   * Outdoor underground services.

Assembly of metal structures of Western part of the Arch:
Metal structures assembled in total – 14316,80 tons

Assembly of metal structures of Eastern part of the Arch:
Metal structures assembled in total – 13712,32 tons

May 14, 2015
May 14, 2015
May 14, 2015
May 14, 2015
May 14, 2015
May 14, 2015