Spent Fuel Processing Facility (SFPF):
- Development of work execution plans (flow sheets) for installation of equipment and systems.
- Unloading of equipment and materials, supply of equipment to the installation area.
- Installation of Technological Process Monitoring and Control System (TP MCS) cabinets.
- Mounting of cable routing structures for PPS, AMS and RMS
- Cable routing.
- Installation of main process equipment:
* Works on modification of shielding door SFP-SD-08 in prem. 403/IS 102 C6.
* Assembling of racks for 200-l drums.
* Installation of the docking device TK-8 cup.
* Installation of crane structures for maintenance, 5 t load-carrying capacity MIS-CR-240 in prem. IS102C9.
* Installation of power supply and control cables of BNG equipment.
* Mounting of ducts, cable laying, connection of control cabinets for ventilation system fire protection valves.
- Supply and installation in the design position of the hot chamber ventilation system equipment.
- Works on RMS gas-aerosol monitoring systems.
- Installation of FGD pipelines.
- Installation of equipment and cable lines of the fire alarm and evacuation control system.
The following activities were also performed at the facility:
- Connecting video cameras and soldering of optic cable from ZVSB to Control Panel 1 at the checkpoint.
- Completing of as-built documents and deliverables for handing-over the relevant stages in accordance with the Contract.
- Development of testing programs for process units and systems and training programs for the Client’s personnel.
The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 152 persons were engaged in the works. 3 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.