ISF-2 construction progress as of November 17, 2016

 

Select another date

Spent Fuel Processing Facility (SFPF):

- Installation of Technological Process Monitoring and Control System (TP MCS) cabinets.
- Mounting of cable routing structures within the SFPF building premises.
- Cable routing within the SFPF building premises.
- Installation of lighting system of SFPF building.
- Installation of supports for lighting and video surveillance systems in “hot cell”, prem. 501.
- Delivery of main process equipment to the installation area – master-slave manipulators, double lid system for handling of 200-l drums, drum transportation systems, suction devices.
- Installation of main process equipment:
     * Installation of shielding door SFP SD 211 (prem. 307).
     * Gateways of small-sized elements SFP TD 220/221 were installed (welding works) into the design position (501/504).
     * Caisson MIS-CE-213 was installed (welding works) in prem. 501.
- Iinstallation of shielding windows SFP-SW-05, SFP-SW-06 and SFP-SW-07 in prem. 501.
- Refurbishment works for the existing equipment:
     * Shielding door SD-04 was painted in prem. 503/501.
     * Preparatory works for Canister Transport Handling System (CHTS).
- Installation of control cabinets for ventilation system fire protection valves.
- I
nstallation of internal protective grounding of SFPF building.
- I
nstallation of video cameras at the building.

 

The following activities were also performed at the facility:

- Installation of supports for video cameras at the SFPF building.
- Installation of PPS security gate near the CSM — the gate leaf was installed into its design position.
- Works on construction of foundations for the PPS lightning protection stands.
- Soldering of optic cable from ZVSB to Control Panel 1 in the checkpoint prem. 203 and along the PPS perimeter
- Completing of as-built documents and deliverables for handing-over the relevant stages in accordance with the Contract.
- Development of testing programs for process units and systems and training programs for the Client’s personnel.
- Individual tests of FT lifting device SFP-TD-211 were completed.

The General Contractor of the project is Holtec. Works at the site are performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, “Kranservis”, “Konditsioner”. In total 198 persons were engaged in the works, as well as 7 units of lorry-loading, earth-moving and lifting machines.