ISF-2 construction progress as of December 21, 2016

Select another date

Spent Fuel Processing Facility (SFPF):

- Installation of Technological Process Monitoring and Control System cabinets in the SFPF building — installation of AWS.
- Mounting of cable routing structures for PPS, AMS and RMS within the SFPF building premises.
- Installation of lighting system within prem.  -101, -103, -104 (level -3,000) at the SFPF
- Installation of main process equipment:
     * Works on modification of a protection hatch (ceiling gate) of prem. IS 102 C6.
     * Assembling of racks for 200-l drums.
     * Preparatory works for installation of transport container trolleys (prem. 114) SFP-TD-05; SFP-TD-06.
     * Installation of pit covers No. 1 and No. 3 SFP-XP-210/211, prem. 501.
- Drilling of holes at flooring 501/107 (installation of additional embedded items for a docking device).
- Electrical installation works on gateway of small-sized elements, holder slide.

The following activities were also performed at the facility:

- Installation of control cabinets for ventilation system fire protection valves.
- Mounting of ducts, cable laying, connection of control cabinets for ventilation system fire protection valves.
- Installation of FGD pipelines.
- Fire protection of ventilation system air ducts.
- Soldering of optic cable from ZVSB to Control Panel 1 at the checkpoint.
- Completing of as-built documents and deliverables for handing-over the relevant stages in accordance with the Contract.
- Development of testing programs for process units and systems and training programs for the Client’s personnel.

The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 193 persons were engaged in the works. 5 units of lorry-loading, earth-moving and lifting machines were also used for fulfilling tasks at the site.

December 21, 2016
December 21, 2016
December 21, 2016
December 21, 2016
December 21, 2016
December 21, 2016