March 21, 2013

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Assembling of basic structures of the arch
- Assembling of hanger supports of crane beams
- Assembling of upper platforms of hoisting towers
- Assembling of a container of jacking system
- Assembling of binding rafters of the cladding
- Assembling of binding rafters of inner lining
- Works on assembling of Floline 70 steel flooring packs were performed
- Profiling of Kalzip panels
- Preparatory works for engineering building were performed

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons
645.3 tons (15.7%) performed

Installation of the Arch roof’s outer cladding:
According to the design, surface area of outer cladding (Stage 1С) - 7,853.9 m2;
Surface area of cladding sections 2, 5 (Stage 2) - 6,098.3 m2;
Surface area of roof cladding before 2nd lifting - 13,952.2
м2.
Overall progress in the Arch outer cladding installation before 2nd lifting – 36.2%

Nearest Events

December 30, 2001 – SSE ChNPP obtained a license for Shelter Object operation and its transformation into an ecologically safe system
January 10, 1979 – commissioning of Power Unit No.2

News distribution