The project was funded by the European Union in the framework of the Annual Action Program for Nuclear Safety 2008 - Part II.
Project objective:
Improving the Radioactive Waste Management, generated as a result of the Nuclear Energy Facilities (Nuclear Power Plants) operation in Ukraine and Chornobyl NPP decommissioning.
Project tasks:
- recommendations development to minimize RAW generation for each of the operating NPPs at the operational stage and for Chornobyl NPP;
- RAW Management System improvement and optimization at the operating NPPs of Ukraine;
- conceptual design of information and analytical system for NNEGC "Energoatom" RAW Management.
The following outcomes were obtained within the Project:
• recommendations for waste processing, conditioning and storage taking into account the specificity of each NPP;
• general and specific recommendations for individual NPPs to minimize waste generated during NPP operation, organizational and technical approaches to waste minimization;
• recommendations for introduction of an integrated Radioactive Waste accounting and control system at operating NPPs;
• Terms of Reference was developed to develop and implement an integrated information and analytical system for RAW accounting and control in the State Enterprise "NNEGC "Energoatom";
• recommendations on decontamination technologies for metal components, building structures, large-size equipment and other materials, liquid waste purification, analysis of the decontamination technologies characteristics and "cost-benefit" analysis was performed;
• concept of large-dimension contaminated components transportation;
• training programs on waste minimization procedures, waste processing and conditioning methods were developed; Training of the Beneficiary / End User staff in accordance with the developed programs was carried out.