Transportation and handover for disposal of RAW packages produced at the Liquid Radioactive Waste Treatment Plant (LRTP) into the Engineered Near-Surface Solid RAW Disposal Facility (ENSDF) commenced on January 31. The first batch in this year – four packages of RAW – was transported to the disposal facility. The further handover of RAW packages to the ENSDF is to be implemented according to the schedule approved between the Chernobyl NPP and State Specialized Enterprise "Central Enterprise for Management of Radioactive Waste" (SSE “CEMRW”) to which the ENSDF belongs. The available RAW packages are transported to make room for the end product storage at the beginning of LRTP operation.
As noted by the Deputy Technical Director (for RAW Management) Oleksandr Skomarokhov, at the beginning of 2018 the Chernobyl NPP has approached the final stage of LRTP commissioning: “A separate permit for the LRTP operation was given to the enterprise in December 2014. Before that all required tests of the LRTP had been carried out. These tests resulted in production of 63 packages with RAW. Four packages were transported to the ENSDF in 2014 to fulfil the whole processing chain of RAW management. Other packages were stored at the LRTP within the end product curing premise in accordance with the permissions of the State Nuclear Regulatory Inspectorate of Ukraine (SNRIU)”.