Spent Fuel Processing Facility (SFPF):
- Mounting of cable routing structures within the SFPF building premises.
- Cable routing within premises.
- Installation of SFPF building lighting system — modification of cable routing at stair flights according to the fire safety requirements.
- Installation of self-leveling floors in premises.
- Installation of main process equipment:
* Installation of security door SFP SD 210 (prem. 501А/IS102c2).
* Installation of security door SFP SD 212 (prem. 312B).
* Installation of security door SFP SD 211 (prem. 307).
- Preparatory works for installation of shielding windows.
- Installation of internal protective grounding of SFPF building.
- Installation of radiation monitoring system — mounting of radiological monitors in the SFPF premises.
Concrete storage modules (CSM):
- Drilling of 464 holes for borescopes at the modules complete.
- Installation of embedded items for borescopes at the modules.
The following activities were also performed at the facility:
- Development of work execution plans (process charts) for installation of equipment and systems.
- Installation of tube protection blocks along the physical protection system (PPS) perimeter complete.
- Installation of sensors along the PPS perimeter.
- Installation of supports for the PPS video cameras at the SFPF building.
- Installation of PPS security gate near the Check Point (ChP) — installation of gate leaf into its design position.
- Installation of PPS security gate near the SFPF — installation of gate leaf into its design position.
- Repair of corrosion-resistant coating of PPS gate.
- Installation of portal monitors for dosimetry control system.
- Installation of access control system (turnstile) at the ChP gatehouse.
- Packing up a set of as-built documents and deliverables to deliver the relevant phases in accordance with the Contract.
- Development of testing programs for process units and systems.
- Development of training programs for the Client’s personnel.
The general Contractor of the project is Holtec. Works at the site are being performed by Holtec subcontractors: CDI, UTEM, UTB, ZEM, EPI, BEM, Kranservis, Konditsioner. In total 182 persons were engaged in the works, as well as 5 units of earth-moving, lorry and lifting machines.