Within the NSC Project at the construction site the following works are being performed:

- Preparatory activities before the sliding;
- Delivery of tertiary steel structures to the site;
- Inspection and assembling of equipment for the Arch sliding;
- Installation of MPFOP anchors of West End wall;
- Installation of sealing anchors;
- Installation of special doors of the Arch;
- Installation of protective shielding of North garage and runways;
- Completion of external and internal cladding installation; works on testing the sealing capacity of the cladding. Progress — 99 %;
- Ventilation system (installation of air ducts is at completion stage, installation of ventilation equipment);

- Main Cranes System (MCS) installation:

* Adjustment of crane-runway girders uipment;
* Testing of MCS (static and dynamic load).

- Arrangement of technological building and auxiliary facilities:

Technological building (TB) — works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls from gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures. Installation of the building face. Progress (construction part) — 98.7%;
* Electrical Equipment Building (EEB) — installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures. Installation of framed steel structures for the face heat insulation and lining;
* Fire Subdivisions Access Lock (FSAL) — polishing, priming, coating and painting of walls and ceilings inside the building;
* Fire water pumping station (FPS) — heat insulation and lining of the face.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch End walls;
* Construction of roads in Local zone — 33%.

Erection of Arch western part steelwork:

Erected in total – 30,552.99 t

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of tertiary steel structures to the site;
- Installation of sliding system control module, inspection and installation of the Arch sliding equipment;
- Installation of anchors of East End wall;
- Installation of sealing anchors at the south-east and at the western end of Deaerator Stack and turbine hall;
- Installation of special doors of the Arch;
- Installation of protective shielding of Northern garage and runways;
- Completion of external and internal cladding installation; works on testing the sealing capacity of the cladding. Progress – 99 %;
- Ventilation system (installation of air ducts is near completion, works have been started on installing ventilation equipment);

- Main Cranes System (MCS) installation:

* adjustment of crane-runway girders and rails;
* preparation for MCS testing.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – works on polishing, priming, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures.  Progress (construction part) — 98.7%;
* Electrical Equipment Building (EEB) – installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures. Installation of framed steel structures for heat insulation of walls and facing of EEB facade;
* Fire Subdivisions Access Lock (FSAL) – polishing, priming, coating and painting of walls and ceilings inside the building;
* Fire water pumping station (FPS) – heat insulation of walls and facing of facade.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch End walls;
* Construction of roads in Local zone — 33%.

Erection of Arch western part steelwork:

Erected in total – 16,136.44 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of tertiary steel structures to the site;
- Installation of sliding system control module, inspection and installation of the Arch sliding equipment;
- Installation of anchors of East End wall;
- Installation of sealing anchors at the south-east and at the western end of Deaerator Stack and turbine hall;
- Installation of special doors of the Arch;
- Installation of protective shielding of Northern garage and runways;
- Completion of external and internal cladding installation; works on testing the sealing capacity of the cladding. Progress – 99 %;
- Ventilation system (installation of air ducts is near completion, works have been started on installing ventilation equipment);

- Main Cranes System (MCS) installation:

* adjustment of crane-runway girders and rails;
* alignment and connection of control panels to the MCS, testing of control systems;
* Preparation for MCS testing.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – works on polishing, priming, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures.  Progress (construction part) — 98.7%;
* Electrical Equipment Building (EEB) – installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures. Installation of framed steel structures for heat insulation of walls and facing of EEB facade;
* Fire Subdivisions Access Lock (FSAL) – polishing, priming, coating and painting of walls and ceilings inside the building;
* Fire water pumping station (FPS) – heat insulation of walls and facing of facade.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch End walls;
* Construction of roads in Local zone — 32%.

Erection of Arch western part steelwork:

Erected in total – 16,126.44 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

October 27, 2016
October 27, 2016
October 27, 2016
October 27, 2016
October 27, 2016
October 27, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of tertiary steel structures to the site;
- Installation of sliding system control module, inspection and installation of the Arch sliding equipment;
- Installation of anchors of East End wall; 
- Installation of sealing anchors at the north-east was completed;
- Installation of sealing anchors at the south-east and at the western end of deaerator stack, and turbine hall;
- Installation of special doors of the Arch; 
- Installation of protective shielding of Northern garage and runways;
- Completion of external and internal cladding installation; works on testing the sealing capacity of the cladding. Progress – 99 %;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress – 98%;
- Completion of NSC ventilation stack installation;

- Main Cranes System (MCS) installation:

* Adjustment of crane-runway girders and rails;
* Alignment and connection of control panels to the MCS, testing of control systems.
* Preparation to MCS testing;
* Testing of 25-t crane for MCS Maintenance garage.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – works on polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures.  Progress (construction part) – 98,6%;
* Electrical Equipment Building (EEB) – installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures. Installation of framed steel structures for heat insulation of walls and facing of EEB facade;
* Fire Subdivisions Access Lock (FSAL) – polishing, pre-coating, coating and painting of walls and ceilings inside the building;
* Fire pumping station (FPS) – leak testing of tanks. Heat insulation of walls and facing of facade.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch End walls;
* Construction of roads in Local zone — 32%.

Erection of Arch western part steelwork:

Erected in total – 16,119.20 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

Select another date

Within the NSC Project at the construction site the following works are being performed:

- delivery of tertiary steel structures to the site;
- mounting of sliding system control module, inspection and installation of the Arch sliding equipment;
- Installation of anchors of East End wall; 
- installation of sealing anchors at the north-east; 
- installation of special doors of the Arch; 
- installation of protective shielding of North garage and runways;
- installation completion of external and internal cladding. Progress — 99%;
- ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress — 98%;
- erection of the NSC ventilation stack was completed.
- installation of sealing anchors.

- Main Cranes System (MCS) installation:

* adjustment of crane-runway girders and rails;
* alignment and connection of control panels to the MCS, testing of control systems;
* Testing of 25-t crane.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TB) — works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls from gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures.  Progress (construction part) — 99.6%.
* Electrical Equipment Building (EEB) — installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures. Installation of framed steel structures for heat insulation of walls and facing of EEB facade.  
* Fire Units Access Lock (FSAL) — polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors. Installation of utilities inside the building. 
* Fire pump station (FPS) — installation of southern fire water tank. Heat insulation and facing.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch End walls;
* Construction of roads in Local zone — 32%.

Erection of Arch western part steelwork:

Erected in total – 16,108.57 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t