* Technological building (TB) — works related to polishing, pre-coating, coating and painting of walls and ceilings inside the building. Installation of supports and fire-fighting water supply pipelines, doors;
* Electrical Equipment Building (EEB) — works related to installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems and steel structures.
* Installation of anchors of the west end wall;
* Pre-assembly and preparation of flashing anchors for installation;
* Preparation of northern (NVC) and southern (SVC) ventilation centers for installation of ventilation equipment. Installation of ventilation equipment piping in NVC and SVC.
* Installation of fire fighting and drinking water pipelines;
* Heat insulation of pipelines of external utilities rack;
* Construction of roads in Local zone — 36%.
* Weight of Arch erected steelwork — 30,552 t;
* Works on moving the Arch into its design position are completed;
* Dismantling of the Arch sliding tracks in the Erection area.
* Technological building (TB) — works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building. Installation of supports and pipelines for fire water supply. The Contractor is installing the doors;
* Electrical Equipment Building (EEB) — installation of fire alarm systems and lighting within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems and metal structures.
* Outdoor cable routes (cable laying);
* Construction of roads in Local zone — 35%.
* Weight of Arch erected steelwork — 30,552 t;
* Works on moving the Arch into its design position are completed.
* The Contractor completed the adjustment of MCS crane-runway girders;
* The MCS tests were completed in the scope envisaged before the sliding.
* Technological building (TB) — works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building. Installation of supports and pipelines for fire water supply. The Contractor is installing doors. Mounting of the frame metal structures for the TB face heat insulation and lining is underway;
* Electrical Equipment Building (EEB) — installation of fire alarm systems and lighting within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures. Mounting of the frame metal structures for the EEB face heat insulation and lining is underway;
* Outdoor cable routes (cable laying);
* Outdoor and underground utility systems (water supply, power supply, sewage system);
* Storm water catching basins;
* The Arch End walls;
* Construction of roads in Local zone — 34%.
* Weight of Arch erected steelwork — 30,552.99 t;
* The NSC ventilation stack is erected;
* Passes were installed at the Arch roof;
* Works on the installation of sealing anchors which were scheduled before the sliding are at the stage of completion;
* The Arch sliding works have been commenced on November 14, 2016.