Within the NSC Project at the construction site the following works are being performed:

 

Technological building and auxiliary facilities:

Technological building (TB) — work on arrangement of the facade of the building eastern part. Installation of cable ducts, cabling. Preparation for crane beam installation for the 20 ton crane. Reassembly of 20 ton crane. Installation of fire alarm system. Works inside the building on polishing, coating, putty, painting of floors, walls and ceilings. Installation of internal pipelines, systems, steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of fire-alarm system. Installation of cable trays, cable laying;
* Access Gateway for Fire brigades – installation of internal networks pipelines, systems, steel structures.;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors.

Works on arranging the NSC internal and external space:

* Arch end walls;
* Walls of pivot mounting gallery;
* Fire fighting water collection pool;
* Installation of fire fighting and drinking water pipelines;
* Arrangement of the thermal insulation of pipelines external engineering networks overpass;
* Construction of roads in Local zone — 38%.

- Erection of Arch steelwork:

* Sealing anchors enlargement, preparation for assembly and installation;
* Installation of north garage shielding;
Preparation of northern (NVC) and southern (SVC) ventilation centers for installation of ventilation equipment. 
* Pipe laying, ventilation equipment installation in NVC and SVC;
* Arch facing preparation for leak test;
* Installation of the MCS trolleys movement system in the northern garage.

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

Technological building and auxiliary facilities:

Technological building (TB) — work on arrangement of the facade of the building eastern part. Installation of cable ducts, cabling. Preparation for crane beam installation for the 20 ton crane. Reassembly of 20 ton crane. Installation of fire alarm system. Works inside the building on polishing, coating, putty, painting of floors, walls and ceilings. Installation of internal pipelines, systems, steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of fire-alarm system. Installation of cable trays, cable laying;
* Access Gateway for Fire brigades – installation of internal networks pipelines, systems, steel structures.;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors.

Works on arranging the NSC internal and external space:

* Installation of fire fighting and drinking water pipelines;
* Arrangement of the thermal insulation of pipelines external engineering networks overpass;
* Construction of roads in Local zone — 37%.

- Erection of Arch steelwork:

* Sealing anchors enlargement, preparation for assembly and installation;
* Installation of north garage shielding;
Preparation of northern (NVC) and southern (SVC) ventilation centers for installation of ventilation equipment. 
* Pipe laying, ventilation equipment installation in NVC and SVC;
* Installation of the MCS trolleys movement system in the northern garage.

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

Technological building and auxiliary facilities:

Technological building (TB) — activities on installing a façade of east side of the building are being carried out. Installation of cable trays, cable laying. Preparation of 20-t crane for mounting. Installation of fire-alarm system. Works on polishing, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building are in progress. Pipe laying of internal circuits, systems, metal structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of fire-alarm system. Installation of cable trays, cable laying;
* Fire Units Access Lock (FSAL) — pipe laying of internal circuits, systems, metal structures. Sub-foundation works for sliding doors;
* Fire Extinguishing Pump Station — installation of pumping equipment and mounting of pumps.

Works on arranging the NSC internal and external space:

* Installation of fire fighting and drinking water pipelines;
* Heat insulation of pipelines of external utilities rack;
* Construction of roads in Local zone — 36,6%.

- Erection of Arch steelwork:

* Pre-assembly works, pre-erection and erection of sealing anchors;
* Installation of north garage shielding;
Preparation of northern (NVC) and southern (SVC) ventilation centers for installation of ventilation equipment.
* Pipe laying, ventilation equipment installation in NVC and SVC.

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

Technological building and auxiliary facilities:

Technological building (TB) — works related to mounting the face of the eastern part of the building are underway. Works related to the installation of cable trunks, cable laying. Electrical installation works related to the installation of 20-ton crane. Installation of fire alarm system. Works related to polishing, pre-coating, coating, pouring and painting of floors, walls and ceilings inside the building. Installation of internal supply pipelines, systems and steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — works related to installation of fire alarm system. Installation of cable trunks supports, cable laying;
* Fire Units Access Lock (FSAL) — installation of internal supply pipelines, systems, steel structures. Installation of the foundation base for sliding doors;
* Fire Extinguishing Pump Station — installation of foundations for pump equipment.

Works on arranging the NSC internal and external space:

* Installation of fire fighting and drinking water pipelines;
* Heat insulation of pipelines of external utilities rack;
* Construction of roads in Local zone — 36%.

- Erection of Arch steelwork:

* Pre-assembly and preparation of flashing anchors for installation;
Preparation of northern (NVC) and southern (SVC) ventilation centers for installation of ventilation equipment. Installation of ventilation equipment piping in NVC and SVC.

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

Technological building and auxiliary facilities:

Technological building (TB) — works related to repair of concrete surfaces, polishing, pre-coating, coating and painting of walls and ceilings inside the building. Works on mounting of the building face are underway.

Activities on closing the tilting panel TP-2:

* Preparation of northern (NVC) and southern (SVC) ventilation centers for installation of ventilation equipment; 
* Installation of ventilation equipment piping in NVC and SVC.

Works on arranging the NSC internal and external space:

* Site cleanup, cleaning of passing routes;
* Reorganization of the Free Access Area (FAA) for a storage area for structures and equipment.