Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system;
* Work to test the main cranes is underway;

Completion of work on external and internal cladding arrangement;
* Arch ventilation system (installation of air ducts and ventilation equipment in the north ventilation centre, south ventilation centre and technological building);
* Works on installation of the sealing membrane are underway;
* Installation of cable ducts along the external Arch stairs construction.

- Technological building and auxiliary facilities:

* Technological building (TB) — work on arrangement of the eastern part of the building façade is close to completion. Installation of the cable ducts, cable laying. Preparation for 20 ton crane testing. Installation of a fire alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Installation of door;
* Electrical Equipment Building (EEB) — installation of the Fire Alarm System, dismantling of the transformers;
* Access Gateway for Fire brigades — installation of internal pipelines networks, arrangement of the external facade;
* Fire Extinguishing Pump Station — works on the electrical cables laying and installation of lighting and alarm system equipment;
* Sewage treatment facilities and pump station of storm water drainage — work on water level lowering  and foundation arrangement. Installation of treatment facilities tanks.

- Works on arranging the NSC internal and external space:

* Installation of fire and household water supply pipelines;
* Arrangement of the site of southern gallery hinged bearing in the Turbine Hall: delivery, assembly and installation of fire extinguishing towers is close to completion; works are carried out to install the design site fencing from the pioneer wall side; water removing tray dismantling;
* Construction of roads in Local zone — 78%.

Select another date

Within the NSC Project at the construction site the following works are being performed:

· Arch

Installation of the following main systems:

-  Power supply system;
-  Ventilation, gas purification and conditioning;
-  Fire safety system;
-  Water supply and sewerage system;
-  Communication and industrial TV system;
-  Physical protection and access control system;
-  Integrated control and monitoring system;
-  System of internal and transport connection;
-  Radiation monitoring system;

The systems of main cranes and small LLM are tested (16 small LLM have been tested so far).
Works on the internal and external lining have been completed.

MUFOP locking anchors are installed on the soffit structures of the West end wall.

The Arch ventilation system (installation of air ducts and ventilation equipment in the northern and southern ventilation centres, as well as in the process building).

Activities on the installation of the sealing membrane are underway.

Installation of cable boxes along the structures of the Arch external ladder.

 · Process building and auxiliary facilities:

- Process building (PB) - activities are carried out on arrangement of the facade of the eastern part of the building. Installation of cable ducts, cable laying.

Connection of 20 ton crane to the control panel. Installation of a fire alarm system. Installation of ventilation system air ducts. Activities on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal network pipelines, systems, metal structures. Installation of doors.

- Electrical Equipment Building - installation of fire alarm system, dismantling of transformers.
- Access Gateway for Fire Brigades - installation of internal networks pipelines, arrangement of external façade.
- Fire Extinguishing Pump Station – electric cable laying and installation of lighting system equipment.
- Sewage treatment facilities and pump station of storm water drainage - work on water level lowering and arrangement of the foundation. Installation of treatment facilities tanks.

Activities on arranging the NSC internal and external space are underway:

- Installation of pipelines for fire and industrial and potable water supply;
- Arrangement of the area of the southern gallery of hinged bearing in the turbine hall; delivery, assembling and installation of fire towers, installing the design fencing of the site from outside of the development wall, dismantling of the drainage gutter;
- Construction of roads and sidewalks in the local zone - 76%.

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Technological building and auxiliary facilities:

* Technological building (TB) — work is carried out on arrangement of the facade of the eastern part of the building. Installation of cable ducts, cable laying. Connection of 20 ton crane to the control panel. Installation of a fire alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Installation of doors;
* Electrical Equipment Building (EEB) — installation of fire alarm system;
* Access Gateway for Fire brigades — installation of internal networks pipelines, installation of equipment and doors;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors;
* Sewage treatment facilities and pump station of storm water drainage — work on water drainage and arrangement of the foundation. Installation of treatment facilities tanks.

- Works on arranging the NSC internal and external space:

* Installation of pipelines for fire and industrial and drinking water supply;
* Arrangement of the site of the southern galleries of hinged bearing near the turbine hall;

* Construction of roads in Local zone — 68%.

- Erection of Arch steelwork:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system;
* Connection of control panels to SOC;

* Works on the internal and external lining are close to completion;
* Arch ventilation system (installation of air ducts and ventilation equipment in the northern and southern ventilation centres, as well as in the technological building);
* Preparation and installation of sealing anchors on the roof of the technological building and access lock for the fire brigades;
* Work on the installation of the sealing membrane are underway;
* Installation of cable boxes along the constructions of the Arch external ladder.

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Technological building and auxiliary facilities:

* Technological building (TB) — work is carried out on arrangement of the facade of the eastern part of the building. Installation of cable ducts, cable laying. Connection of 20 ton crane to the control panel. Installation of a fire alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Installation of doors;
* Electrical Equipment Building (EEB) — installation of Fire Alarm System;
* Access Gateway for Fire brigades — installation of internal networks pipelines, installation of the equipment and doors;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors;
* Sewage treatment facilities and pump station of storm water drainage — work on water drainage and arrangement of the foundation. Installation of treatment facilities tanks.

- Works on arranging the NSC internal and external space:

* Installation of pipelines for fire and industrial and drinking water supply;
* Arrangement of the site of the southern galleries of hinged bearing near the turbine hall;

* Construction of roads in Local zone — 68%.

- Erection of Arch steelwork:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system;
* Installation of MCS control panels in the central control panel. Connection of control panels to MCS. Works installation of small load-lifting mechanisms in the technological building are under way;

* Works on the internal and external lining are close to completion;
* Arch ventilation system (installation of air ducts and ventilation equipment in the northern and southern ventilation centres, as well as in the technological building);
* Preparation and installation of sealing anchors on the roof of the technological building and access lock for the fire brigades;
* Work on the installation of the sealing membrane are underway;
* Installation of cable boxes along the constructions of the Arch external ladder.

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Technological building and auxiliary facilities:

* Technological building (TB) — work associated with arrangement of the facade of the building eastern part. Installation of cable ducts, cabling is underway. Crane beams for the 20 ton crane are being installed. Reassembly of 20 ton crane. The crane has been lifted to the design reference mark. Installation of Fire Alarm System. Installation of air ducts of the ventilation system. Works inside the building on polishing, priming, filling up with putty, pouring, painting of floors, walls and ceilings are underway. Installation of internal pipelines, systems, steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of Fire Alarm System. Installation of cable ducts, cable laying;
* Access Gateway for Fire brigades — installation of internal networks pipelines, installation of the equipment and doors;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors;
* Storm Water Dispersal Plant — activities on water drawdown and foundation construction, dewatering of the site sump. The tanks of dispersal plant are being installed.

- Works on arranging the NSC internal and external space:

* Installation of fire fighting and drinking water pipelines;
* Arrangement of Arch end walls;
* Arrangement of the area for southern gallery of articulated supports near the turbine hall;

* Construction of roads in Local zone — 65%.

- Erection of Arch steelwork:

* Installation of the following main systems:
• Power supply system;
Ventilation, gas purification and conditioning;
Fire safety system;
Water supply and sewerage system;
Communication and industrial TV system;
Physical protection and access control system;
Integrated management and control system;
System of internal and transport connection;
Radiation monitoring system;
* The Contractor also completed installation of the MCS trolleys moving system in the northern garage. The MCS control cabinets are being installed in the central control room. Connection of control boards to the central control room;

* Work is underway to install small lifting devices in the technological building;
* Completion of external and internal facing;
* Preparation for installation and installation of sealing anchors on the roof of TB and Access Gateway for Fire Brigades;
* Installation of the sealing membrane is underway.

May 25, 2017
May 25, 2017
May 25, 2017
May 25, 2017
May 25, 2017
May 25, 2017
May 25, 2017