Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Preliminary assembling of the Arch metal structure panels;
- Assembling of the Arch metal structures;
- Installation of casing girders;
- Assembling of external and internal casing of the Arch;
- Reinforcing and concreting the foundation frame of the serviced area (northern trench);
- Activities on arranging an engineering building and auxiliary facilities.

Assembling of metal structures of the Arch (till Lifting No.3)
Under design - 2286 tons, performed - 657.83 tons (28.78%)

Arch Ground Beam in the Transfer Zone:
Concrete: under design - 7677.6 m3, placed - 6561.5 m3 (85.46%); 
Reinforcing steel: under design - 1593.128 tons, manufactured - 1504.940 tons (94.4%)

Arrangement of foundations in the Arch’s serviced area (northern slip):
Concrete: under design - 5,674.2 m3, placed - 1,653 m3 (29.13%); 
Reinforcing steel: under design - 1198,678 tons, manufactured - 770,674 tons (64.28%

 

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Preliminary assembling of the Arch metal structure panels;
- Assembling of the Arch metal structures;
- Installation of casing girders;
- Assembling of external and internal casing of the Arch;
- Reinforcing and concreting the foundation frame of the serviced area (northern trench);
- Activities on arranging an engineering building and auxiliary facilities.

Assembling of metal structures of the Arch (till Lifting No.3)
Under design - 2286 tons, performed - 538.97 tons (23.57%)

Arrangement of foundations in the Arch’s serviced area (northern slip):
Concrete: under design - 5,674.2 m3, placed - 1,653 m3 (29.13%); 
Reinforcing steel: under design - 1198,678 tons, manufactured - 770,674 tons (64.28%

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Preliminary assembling of the Arch metal structure panels;
- Assembling of the Arch metal structures;
- Installation of casing girders;
- Assembling of external and internal casing of the Arch;
- Reinforcing and concreting the foundation frame of the serviced area (northern trench);
- Activities on arranging an engineering building and auxiliary facilities.

Assembling of metal structures of the Arch (till Lifting No.3)
Under design - 2286 tons, performed - 460.88 tons (20.12%)

Arrangement of foundations in the Arch’s serviced area (northern slip):
Concrete: under design - 5,674.2 m3, placed - 1290 m3 (22.73%); 
Reinforcing steel: under design - 1198,678 tons, manufactured - 722,749 tons (60.29%)

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Preliminary assembling of the Arch metal structure panels;
- Assembling of the Arch metal structures;
- Installation of casing girders;
- Displacement of the hoisting towers;
- Assembling of external and internal casing of the Arch;
- Reinforcing and concreting the foundation frame of the serviced area (northern trench);
- Activities on arranging an engineering building and auxiliary facilities.

Assembling of metal structures of the Arch (till Lifting No.3)
Under design - 2286 tons, performed - 389.88 tons (17.05%)

Arrangement of foundations in the Arch’s serviced area (northern slip):
Concrete: under design - 5,674.2 m3, placed - 754 m3 (13.28%); 
Reinforcing steel: under design - 1,198.678 tons, manufactured - 602.778 tons (50.28%)

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling of panels of metal structures of the Arch;
- Installation of girders for casing;
- Dismantling of jacking system containers;
- Displacement of lifting towers;
- Assembling of external and internal casing of the Arch;
- Reinforcement and concreting of the serviced area ground beam (northern slip);
- Operations on arranging an engineering building and auxiliary structures.

Assembling of metal structures of the Arch (till Lifting No.3)
Under design - 2286 tons, performed - 290.26 tons (12.69%)

Arrangement of foundations in the Arch’s serviced area (northern slip):
Concrete: under design - 5,674.2 m3, placed - 686 m3 (12.10%); 
Reinforcing steel: under design - 1,251.609 tons, manufactured - 452.428 tons (36.15%)