Within the NSC Project at the construction site the following works are being performed:
- Preliminary assembling of the Arch metal structure panels;
- Assembling of the Arch metal structures;
- Installation of casing girders;
- Assembling of external and internal casing of the Arch;
- Reinforcing and concreting the foundation frame of the serviced area (northern trench);
- Activities on arranging an engineering building and auxiliary facilities.
Assembling of metal structures of the Arch (till Lifting No.3)
Under design - 2286 tons, performed - 657.83 tons (28.78%)
Arch Ground Beam in the Transfer Zone:
Concrete: under design - 7677.6 m3, placed - 6561.5 m3 (85.46%);
Reinforcing steel: under design - 1593.128 tons, manufactured - 1504.940 tons (94.4%)
Arrangement of foundations in the Arch’s serviced area (northern slip):
Concrete: under design - 5,674.2 m3, placed - 1,653 m3 (29.13%);
Reinforcing steel: under design - 1198,678 tons, manufactured - 770,674 tons (64.28%)