Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Arrangement of the service zone foundations (foundation frame of Northern trench);
- Arrangement of engineering building and auxiliary facilities.

Assembling of the Arch West part:
Total weight of metal structures – 3,323 tons.
Metal structures assembled in total –  1,674.17 tons (50.38%).

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,392.5 tons
Metal structures assembled in total – 12,213.31 tons (91.2%).

  

January 30, 2014
January 30, 2014
January 30, 2014
January 30, 2014
January 30, 2014

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Assembling of bearing and hoisting towers (temporary structures for  Western part of the Arch);
- Arrangement of the service zone foundations (foundation frame of Northern trench);
- Arrangement of engineering building and auxiliary facilities.

Assembling of the Arch West part:
Total weight of metal structures – 3,323 tons.
Metal structures assembled in total –  1,655.58 tons (49.82%).

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,392.5 tons.
Metal structures assembled in total – 12,213.31 tons (91.2%).

 

January 23, 2014
January 23, 2014
January 23, 2014
January 23, 2014
January 23, 2014
January 23, 2014

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Assembling of bearing and hoisting towers (temporary structures for Western part of the Arch);
- Arrangement of the service zone foundations;
- Arrangement of engineering building and auxiliary facilities.

Assembling of the Arch West part:
Total weight of metal structures – 3,323 tons.
Metal structures assembled in total –  1,535.26 tons (46.2%).

 

January 16, 2014
January 16, 2014
January 16, 2014
January 16, 2014
January 16, 2014
January 16, 2014

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to site and completing the basic structures of Western part of the Arch;
- Assembling of basic metal structure panels of Western part of the Arch;
- Assembling of bearing towers and locking mechanisms (temporary structures for Western Arch);
- Installation of internal casing girders;
- Assembling of external casing of the Arch;
- Arranging an engineering building and auxiliary facilities.

Assembling of the Arch West part:
Total weight of metal structures – 3,323 tons.
Metal structures assembled in total –  1,476.48 tons (44.43%).

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 12,818.593 tons.
Metal structures assembled in total – 12,174.69 tons (94.98%).

Foundations in the Arch service area (north trench):
Design volume of concrete – 5,674.2 m
3, placed – 5,221.5 m3 (92.02%); 
Design amount of re-bars - 1,198.678 tons, produced – 1,198.678 tons (100%).

Foundations in the Arch service area (south trench):
Design volume of concrete – 1,207.7 m
3, placed – 1,237.0 m3 (102.43%); 
Number of piles – design number: 216 pcs., performed up to design reference mark: 58 pcs. (26.85%).
 