Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Assembling of bearing and hoisting towers;
- Preparation of containers for jacking the West Part of the Arch;
- Preparation of equipment for movement of the Eastern part of the Arch into the stand-by area;
- Preliminary assembling of casing panels;
- Installation of casing girders;
- Assembling of external and internal casing;
- Arrangement of the service zone foundations (foundation frame of Northern trench);
- Isntallation of CFA piles of service area foundation (Southern trench);
- Arrangement of engineering building and auxiliary facilities. 

Assembling of the Arch West part:
Total weight of metal structures – 3,323 tons.
Metal structures assembled in total – 2,667.22 tons (80.27%).

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,392.5 tons
Metal structures assembled in total – 12,732.84 tons (94.0%).

Foundations in the Arch service area:
Design volume of concrete – 11,795.73 m3, placed – 5,545.0 m3 (47.0%); 
Design amount of rebars - 2,447.009 tons, 
rebar fabrication – 1,283.333 tons (52.44%).

Construction of the CFA piles (south foundation):
As per the design – 216 piles; completed till design – 92 piles (42.59%)

 

March 06, 2014
March 06, 2014
March 06, 2014
March 06, 2014
March 06, 2014
March 06, 2014
 

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Assembling of bearing and hoisting towers;
- Preparation of containers for jacking the West Part of the Arch;
- Preparation of equipment for movement of the Eastern part of the Arch into the stand-by area;
- Preliminary assembling of casing panels;
- Installation of casing girders;
- Assembling of external and internal casing;
- Arrangement of the service zone foundations (foundation frame of Northern trench);
- Isntallation of CFA piles of service area foundation (Southern trench);
- Arrangement of engineering building and auxiliary facilities. 

Assembling of the Arch West part:
Total weight of metal structures – 3,323 tons.
Metal structures assembled in total – 2,274.58 tons (74.47%).

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,392.5 tons
Metal structures assembled in total – 12,612.32 tons (93.1%).

Foundations in the Arch service area:
Design volume of concrete – 11,795.73 m3, placed – 5,416.0 m3 (45.91%); 
Design amount of rebars - 2,447.009 tons,
rebar fabrication – 1,283.333 tons (52.44%).

Construction of the CFA piles (south foundation):
As per the design – 216 piles; completed till design – 88 piles (40.74%)

 

February 27, 2014
February 27, 2014
February 27, 2014
February 27, 2014
February 27, 2014
February 27, 2014
 

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Assembling of bearing and hoisting towers;
- Preparation of containers for jacking the West Part of the Arch; 
- Preliminary assembling of casing panels;
- Installation of casing girders;
- Assembling of external and internal casing;
- Arrangement of the service zone foundations (foundation frame of Northern trench);
- Isntallation of CFA piles of service area foundation (Southern trench);
- Arrangement of engineering building and auxiliary facilities. 

Assembling of the Arch West part:
Total weight of metal structures – 3,323 tons.
Metal structures assembled in total – 2,262.68 tons (68.09%).

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,392.5 tons
Metal structures assembled in total – 12,514.69 tons (92.54%).

Foundations in the Arch service area (north trench):
Design volume of concrete – 5,674.2 m3, placed – 5,353.0 m3 (94.34%); 
Design amount of re-bars - 1,198.678 tons,
rebar fabrication – 1,198.678 tons (100%).

Construction of the CFA piles (south foundation):
As per the design – 216 piles; completed till design – 82 piles (37.96%)

 

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Assembling of bearing and hoisting towers; 
- Preliminary assembling of casing panels;
- Installation of casing girders;
- Assembling of external and internal casing;
- Arrangement of the service zone foundations (foundation frame of Northern trench);
- Isntallation of CFA piles of service area foundation (Southern trench);
- Arrangement of engineering building and auxiliary facilities. 

Assembling of the Arch West part:
Total weight of metal structures – 3,323 tons.
Metal structures assembled in total – 2,058.0 tons (61.93%).

Foundations in the Arch service area (north trench):
Design volume of concrete – 5,674.2 m3, placed – 5,353.0 m3 94.34%); 
Design amount of re-bars - 1,198.678 tons, produced – 1,198.678 tons (100%).

Construction of the CFA piles (south foundation):
As per the design – 216 piles; completed till design – 70 piles (32.41%)

 

February 13, 2014
February 13, 2014
February 13, 2014
February 13, 2014
February 13, 2014
February 13, 2014

 Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Delivery to the site and completing the basic structures of Western part of the Arch;
- Assembling of basic structures of Western part of the Arch;
- Assembling of bearing and hoisting towers; 
- Preassembling of cladding panels;
- Arrangement of the service zone foundations (foundation frame of Northern trench);
- Isntallation of CFA piles of service area foundation (Southern trench);
- Arrangement of engineering building and auxiliary facilities. 

Assembling of the Arch West part:
Total weight of metal structures – 3,323 tons.
Metal structures assembled in total –  1,865.49 tons (56.14%).

Assembling of the Arch East part:
Total weight of metal structures, including secondary structures, bolts and crane-runway beams – 13,392.5 tons
Metal structures assembled in total – 12,213.31 tons (91.2%).

Construction of the CFA piles (south foundation):
As per the design – 216 piles; completed till design – 62 piles (28.7%)

 

February 06, 2014
February 06, 2014
February 06, 2014
February 06, 2014
February 06, 2014
February 06, 2014