Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Preparatory work before the sealing anchors and the sealing membrane installation at the block V.

- Technological building and auxiliary facilities:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system
* Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

- Works on arranging the NSC internal and external space:

* Completion of fire and household water supply pipelines installation;
* Site improvement activity;
* Weather station establishment.

Other activity:

* Dismantling of the Turbine Hall light roof.

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

Completion of work on external and internal Arch lining arrangement;
Work to prepare and to test the main cranes system is underway;
* Preparatory work before the sealing anchors and the sealing membrane installation.

- Technological building and auxiliary facilities:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system
* Interior finishing of premises.

- Works on arranging the NSC internal and external space:

* Completion of fire and household water supply pipelines installation;
* Arrangement of roads and sidewalks within the local zone is close to completion — 98%;

* Site improvement activity;
* Weather station establishment.

Other activity:

* Dismantling of the Turbine Hall light roof.

October 26, 2017
October 26, 2017
October 26, 2017
October 26, 2017
October 26, 2017
October 26, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system;
* Work to prepare and to test the main cranes system is underway;

Completion of work on external and internal cladding arrangement;
* Arch ventilation system and auxiliary constructions (installation of supports, air ducts and ventilation equipment).

- Technological building and auxiliary facilities:

* Technological building (TB) — Installation of the cable ducts and cable laying, installation of gates. Installation of Fire Alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Preparation for RAW containers grippers testing using the 20 tons crane;
* Electrical Equipment Building (EEB) — installation of the Fire Alarm System, ventilation, installation of the electrical equipment. Work to install the hot water supply and heat supply systems is underway;
* Access Gateway for Fire brigades — installation of ventilation ducts, arrangement of the external facade, interior furnishing;
* Fire Extinguishing Pump Station — scaffolding dismantling;
* Diesel electric power station site — electrical equipment connection. Installation of a fueling station with a reserve tank of diesel fuel
* Sewage treatment facilities and pump station of storm water drainage — preparation for individual testing.

- Works on arranging the NSC internal and external space:

* Completion of fire and household water supply pipelines installation;
* Turbine Hall light roof dismantling;

* Construction of roads in Local zone — 100%.

 

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system;
* Work to prepare and to test the main cranes system is underway;

Completion of work on external and internal cladding arrangement;
* Arch ventilation system (installation of air ducts and ventilation equipment in the north ventilation centre, south ventilation centre and technological building);
* Works on installation of the sealing membrane are underway.

- Technological building and auxiliary facilities:

* Technological building (TB) — work on arrangement of the eastern part of the building facade is close to completion. Installation of the cable ducts and cable laying, installation of gates. Installation of Fire Alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Preparation for RAW containers grippers testing using the 20 tons crane;
* Electrical Equipment Building (EEB) — installation of the Fire Alarm System, ventilation, installation of the electrical equipment. Work to install the hot water supply and heat supply systems is underway;
* Access Gateway for Fire brigades — installation of internal networks pipelines, ventilation, arrangement of the external facade, interior furnishing;
* Fire Extinguishing Pump Station — completion of the interior furnishing;
* Sewage treatment facilities and pump station of storm water drainage — installation of treatment facilities tanks. Backfilling of the sewage pump station with sand with a layer-by-layer compaction.

- Works on arranging the NSC internal and external space:

* Completion of fire and household water supply pipelines installation;
* Turbine Hall light roof dismantling;

* Construction of roads in Local zone — 87%.

September 20, 2017
September 20, 2017
September 20, 2017
September 20, 2017
September 20, 2017
September 20, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system;
* Work to prepare and to test the main cranes system is underway;

Completion of work on external and internal cladding arrangement;
* Arch ventilation system (installation of air ducts and ventilation equipment in the north ventilation centre, south ventilation centre and technological building);
* Works on installation of the sealing membrane are underway.

- Technological building and auxiliary facilities:

* Technological building (TB) — work on arrangement of the eastern part of the building façade is close to completion. Installation of the cable ducts and cable laying. Installation of Fire Alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Preparation for RAW containers grippers testing using the 20 tons crane;
* Electrical Equipment Building (EEB) — installation of the Fire Alarm System, installation of the electrical equipment. Work has started to install the hot water supply and heat supply systems;
* Access Gateway for Fire brigades — installation of internal pipelines networks, arrangement of the external facade;
* Fire Extinguishing Pump Station — the electrical works are underway;
* Sewage treatment facilities and pump station of storm water drainage — installation of treatment facilities tanks. Backfilling with sand with a layer-by-layer compaction, preparation for testing.

- Works on arranging the NSC internal and external space:

* Installation of fire and household water supply pipelines;
* Arrangement of the site of southern gallery hinged bearing in the Turbine Hall: Turbine Hall light roof dismantling is underway;

* Construction of roads in Local zone — 85%.