Within the NSC Project at the construction site the following works are being performed:
- Load transfer from the Arch lifting system jacks to the locking devices;
- Arrangement of inclined piles in the serviced area (northern slip foundations)
- Work commencement on assembling of external casing of the Arch (end wall)
- Reinforcement of the serviced area foundation (northern slip);
- Operations on arranging an engineering building.
Assembling of metal structures of the Arch (till Lifting No.3)
Under design – 1,170 tons, performed – 36 tons (2%)
Arrangement of base concrete and insertion of inclined piles within serviced area (northern slip):
- Design concrete volume – 1,060 m3, placed – 1,058 m3 (99.81%);
- Design pile amount – 208 piles, placed till design mark – 163 piles (78,36%)