Within the NSC Project at the construction site the following works are being performed:
- Completion of the Second Lifting of the Arch:
-- Dismantling of pivoting supports;
-- Assembly of locking devices;
-- Load transfer from the lifting system jacks to the locking devices (25% of load is transferred to the locking devices);
- Arrangement of inclined piles in the serviced area (northern slip foundations) – 154 piles of 208 (74%).
- Reinforcement of the serviced area foundation (northern slip).
- Operations on arranging an engineering building.
Arrangement of base concrete and insertion of inclined piles within serviced area (northern slip):
- Design concrete volume – 1,060 m3, placed – 1,058 m3 (99.81%);
- Design pile amount – 208 piles, placed till design mark – 154 piles (74%)