Within the NSC Project at the construction site the following works are being performed:
- Completion of works on Second Lifting of the Arch
- Arrangement of inclined piles in the serviced area (northern slip foundations)
- Reinforcement of the serviced area (northern slip)
- Activities on arranging an engineering building

Arrangement of base concrete and insertion of inclined piles within serviced area (northern slip):
- Design concrete volume – 1,060 m3, placed – 1,058 m3 (99.81%);
- Design pile amount – 208 piles, placed till design mark – 138 piles (66.35%)