Within the NSC Project at the construction site the following works are being performed:
- Second lifting of the Arch is performed
- Arrangement of inclined piles in the serviced area (northern slip foundations)
- Reinforcement of the serviced area (northern slip)
- Activities on arranging an engineering building
Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 3,788.6 tons
3,788.6 tons (100%) performed
Mounting of the roof covering of the Arch:
Surface area of roof cladding before 2nd lifting - 13,952.2 m2, 96.37% performed.
Surface area of internal cladding before 2nd lifting – 12,468.15 m2, 89.26% performed
Arrangement of base concrete and insertion of inclined piles within serviced area (northern slip):
- Design concrete volume – 1,060 m3, placed – 1,058 m3 (99.81%);
- Design pile amount – 208 piles, placed till design mark – 122 piles (58.65%)