Within the NSC Project at the construction site the following works are being performed:

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons
3,720.63 tons (90.81%) performed

Installation of the Arch roof’s outer cladding:
Surface area of roof cladding before 2nd lifting - 13,952.2 м2.
Overall progress in the Arch outer cladding installation before 2nd lifting – 79%

Arrangement of base concrete and insertion of inclined piles within serviced area (northern slip):
- Design concrete volume – 1,060 m3, placed – 1,058 m3 (99.81%);
- Design pile amount – 208 piles, placed till design mark – 74 piles (35.6%)