May 16, 2013

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Assembling of basic and supporting structures of the Arch;
- Assembling of guiding slide supports for Lifting No.2;
- Assembling of air ducts of the Arch;
- Assembling of crane beams of the main crane system;
- Assembling of external and internal casing of the Arch;
- Arrangement of base concrete for pile field in the serviced area (northern slip foundations);
- Arrangement of inclined piles in the serviced area (northern slip foundations);
- Excavations on arranging an engineering building.

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons
3,593.38 tons (87,7%) performed

Installation of the Arch roof’s outer cladding:
Surface area of roof cladding before 2nd lifting - 13,952.2 м2.
Overall progress in the Arch outer cladding installation before 2nd lifting – 53.3%

Arrangement of base concrete and insertion of inclined piles within serviced area (northern slip):
- Design concrete volume – 1,060 m3, placed – 773 m3 (73%);
- Design pile amount – 208 piles, placed till design mark – 54 piles (26%)