April 25, 2013

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Assembling of basic structures of the Arch;
- Assembling of external bearers of the end wall;
- Cementing of jacking tower anchors;
- Assembling of hanger supports of crane beams;
- Assembling of crane beams;
- Assembling of Floline 70 steel flooring packs and omega profile;
- Assembling of Floline 40 steel flooring;
- Assembling of Kalzip panels of inner lining;
- Arrangement of base concrete for pile field in the serviced area (northern slip);
- Arrangement of inclined piles (northern slip)
- Excavations on arranging engineering building.

Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons
2,759.79 tons (67.4%) performed

Installation of the Arch roof’s outer cladding:
According to the design, surface area of outer cladding (Stage 1С) - 7,853.9 m2;
Surface area of cladding sections 2, 5 (Stage 2) - 6,098.3 m2;
Surface area of roof cladding before 2nd lifting - 13,952.2
м2.
Overall progress in the Arch outer cladding installation before 2nd lifting – 53.3%

Arrangement of base concrete and insertion of inclined piles within serviced area (northern slip):
- Design concrete volume – 1,060 m3, placed – 254 m3 (24%);
- Design pile amount – 208 piles, placed till design mark – 14 piles (6.7%)