Within the NSC Project at the construction site the following works are being performed:
- Assembling of basic structures of the Arch;
- Assembling of external bearers of the end wall;
- Cementing of jacking tower anchors. Assembling of plates for movable supports
- Assembling of hanger supports of crane beams;
- Assembling of crane beams;
- Assembling of Floline 70 steel flooring packs and omega profile;
- Assembling of Floline 40 steel flooring;
- Assembling of Kalzip panels of inner lining;
- Arrangement of base concrete for pile field in the serviced area (northern slip);
- Excavations on arranging engineering building.
Assembly of the Arch metal structures (for 2nd lifting)
According to the design - 4,097 tons
2046,66 tons (50%) performed
Installation of the Arch roof’s outer cladding:
According to the design, surface area of outer cladding (Stage 1С) - 7,853.9 m2;
Surface area of cladding sections 2, 5 (Stage 2) - 6,098.3 m2;
Surface area of roof cladding before 2nd lifting - 13,952.2 м2.
Overall progress in the Arch outer cladding installation before 2nd lifting – 46,12%