NSC construction progress as of January 11, 2018

Select another date

Erection of Arch steelwork

• Installation of the sealing anchor beams on the roofs of Block V;
• Installation of the membrane on the roof of Block V.

Technological building and auxiliary facilities

• Installation of the following main systems:
- Power supply system;
- Ventilation, gas purification and conditioning;
- Fire safety system;
- Water supply and sewerage system;
- Communication and industrial TV system;
- Physical protection and access control system;
- Integrated management and control system;
- System of internal and transport connection;
- Radiation monitoring system;
• Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

Fire extinguishing pump station building with tanks

• Electrical fitting works are in progress. Installation of a system of exhaust gases from diesel-driven pumps.

Works on arranging the NSC internal and external space

• Pipelines installation;
• Weather station establishment.

Other activity

• Dismantling of the Turbine Hall light roof.