NSC construction progress as of November 16, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Preparatory work before the sealing anchors and the sealing membrane installation at the block V.

- Technological building and auxiliary facilities:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system
* Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the TB an FBAL is underway.

- Works on arranging the NSC internal and external space:

* Completion of fire and household water supply pipelines installation;
* Site improvement activity;
* Weather station establishment.

Other activity:

* Dismantling of the Turbine Hall light roof;
* Drilling of holes at Block V for subsequent installation of sealing anchors.