Within the NSC Project at the construction site the following works are being performed:
- Erection of Arch steelwork:
* Completion of work on external and internal Arch lining arrangement;
* Work to prepare and to test the main cranes system is underway;
* Preparatory work before the sealing anchors and the sealing membrane installation.
- Technological building and auxiliary facilities:
* Installation of the following main systems:
• Power supply system;
• Ventilation, gas purification and conditioning;
• Fire safety system;
• Water supply and sewerage system;
• Communication and industrial TV system;
• Physical protection and access control system;
• Integrated management and control system;
• System of internal and transport connection;
• Radiation monitoring system
* Interior finishing of premises.
- Works on arranging the NSC internal and external space:
* Completion of fire and household water supply pipelines installation;
* Arrangement of roads and sidewalks within the local zone is close to completion — 98%;
* Site improvement activity;
* Weather station establishment.
- Other activity:
* Dismantling of the Turbine Hall light roof.