NSC construction progress as of October 19, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system;
* Work to prepare and to test the main cranes system is underway;

Completion of work on external and internal cladding arrangement;
* Arch ventilation system and auxiliary constructions (installation of supports, air ducts and ventilation equipment).

- Technological building and auxiliary facilities:

* Technological building (TB) — Installation of the cable ducts and cable laying, installation of gates. Installation of Fire Alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Preparation for RAW containers grippers testing using the 20 tons crane;
* Electrical Equipment Building (EEB) — installation of the Fire Alarm System, ventilation, installation of the electrical equipment. Work to install the hot water supply and heat supply systems is underway;
* Access Gateway for Fire brigades — installation of ventilation ducts, arrangement of the external facade, interior furnishing;
* Fire Extinguishing Pump Station — scaffolding dismantling;
* Diesel electric power station site — electrical equipment connection. Installation of a fueling station with a reserve tank of diesel fuel
* Sewage treatment facilities and pump station of storm water drainage — preparation for individual testing.

- Works on arranging the NSC internal and external space:

* Completion of fire and household water supply pipelines installation;
* Turbine Hall light roof dismantling;

* Construction of roads in Local zone — 100%.