Within the NSC Project at the construction site the following works are being performed:
- Erection of Arch steelwork:
* Installation of the following main systems:
• Power supply system;
• Ventilation, gas purification and conditioning;
• Fire safety system;
• Water supply and sewerage system;
• Communication and industrial TV system;
• Physical protection and access control system;
• Integrated management and control system;
• System of internal and transport connection;
• Radiation monitoring system;
* Work to prepare and to test the main cranes system is underway;
* Completion of work on external and internal cladding arrangement;
* Arch ventilation system (installation of air ducts and ventilation equipment in the north ventilation centre, south ventilation centre and technological building);
* Works on installation of the sealing membrane are underway.
- Technological building and auxiliary facilities:
* Technological building (TB) — work on arrangement of the eastern part of the building facade is close to completion. Installation of the cable ducts and cable laying, installation of gates. Installation of Fire Alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Preparation for RAW containers grippers testing using the 20 tons crane;
* Electrical Equipment Building (EEB) — installation of the Fire Alarm System, ventilation, installation of the electrical equipment. Work to install the hot water supply and heat supply systems is underway;
* Access Gateway for Fire brigades — installation of internal networks pipelines, ventilation, arrangement of the external facade, interior furnishing;
* Fire Extinguishing Pump Station — completion of the interior furnishing;
* Sewage treatment facilities and pump station of storm water drainage — installation of treatment facilities tanks. Backfilling of the sewage pump station with sand with a layer-by-layer compaction.
- Works on arranging the NSC internal and external space:
* Completion of fire and household water supply pipelines installation;
* Turbine Hall light roof dismantling;
* Construction of roads in Local zone — 87%.