Within the NSC Project at the construction site the following works are being performed:
- Erection of Arch steelwork:
* Installation of the following main systems:
• Power supply system;
• Ventilation, gas purification and conditioning;
• Fire safety system;
• Water supply and sewerage system;
• Communication and industrial TV system;
• Physical protection and access control system;
• Integrated management and control system;
• System of internal and transport connection;
• Radiation monitoring system;
* Work to test the main cranes is underway;
* Completion of work on external and internal cladding arrangement;
* Arch ventilation system (installation of air ducts and ventilation equipment in the north ventilation centre, south ventilation centre and technological building);
* Works on installation of the sealing membrane are underway.
- Technological building and auxiliary facilities:
* Technological building (TB) — work on arrangement of the eastern part of the building façade is close to completion. Installation of the cable ducts, cable laying. 20 ton crane in prem 123 was tested. Installation of a fire alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions;
* Electrical Equipment Building (EEB) — installation of the Fire Alarm System, installation and connection of new transformers installation of electrical equipment. Installation of hot water supply and heat supply systems has started;
* Access Gateway for Fire brigades — installation of internal pipelines networks, arrangement of the external facade;
* Fire Extinguishing Pump Station — electrical work is underway;
* Sewage treatment facilities and pump station of storm water drainage — installation of treatment facilities tanks. Back filling of sand with a layer-by-layer compaction. Work to prepare the foundation under reservoirs of absorption filters is underway.
- Works on arranging the NSC internal and external space:
* Installation of fire and household water supply pipelines;
* Arrangement of the southern gallery hinged bearing near the Turbine Hall: delivery, assembly and installation of fire extinguishing towers; works are carried out to install the design site fencing from the pioneer wall side, water removing tray dismantling;
* Preparatory work before the Turbine Hall roof dismantling;
* Construction of roads in Local zone — 79%.