NSC construction progress as of August 03, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Erection of Arch steelwork:

* Installation of the following main systems:
   • Power supply system;
   • Ventilation, gas purification and conditioning;
   • Fire safety system;
   • Water supply and sewerage system;
   • Communication and industrial TV system;
   • Physical protection and access control system;
   • Integrated management and control system;
   • System of internal and transport connection;
   • Radiation monitoring system;
* Work to test the main cranes is underway;

Completion of work on external and internal cladding arrangement;
* Arch ventilation system (installation of air ducts and ventilation equipment in the north ventilation centre, south ventilation centre and technological building);
* Works on installation of the sealing membrane are underway;
* Installation of cable ducts along the Arch external stairs constructions.

- Technological building and auxiliary facilities:

* Technological building (TB) — work on arrangement of the eastern part of the building facade is close to completion. Installation of the cable ducts. Preparation and testing of 20 ton crane. Installation of a fire alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Installation of doors;
* Electrical Equipment Building (EEB) — installation of the Fire Alarm System, installation of new transformers;
* Access Gateway for Fire brigades — installation of internal pipelines networks, arrangement of the external facade;
* Fire Extinguishing Pump Station — works on the electrical cables laying and installation of lighting and alarm system equipment;
* Sewage treatment facilities and pump station of storm water drainage — work on water level lowering  and foundation arrangement. Installation of treatment facilities tanks.

- Works on arranging the NSC internal and external space:

* Installation of fire and household water supply pipelines;
* Arrangement of the southern gallery hinged bearing near the Turbine Hall: delivery, assembly and installation of fire extinguishing towers; works are carried out to install the design site fencing from the pioneer wall side, water removing tray dismantling;
* Preparatory work before the Turbine Hall roof dismantling;
* Construction of roads in Local zone — 79%.