NSC construction progress as of July 19, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

· Arch

Installation of the following main systems:

-  Power supply system;
-  Ventilation, gas purification and conditioning;
-  Fire safety system;
-  Water supply and sewerage system;
-  Communication and industrial TV system;
-  Physical protection and access control system;
-  Integrated control and monitoring system;
-  System of internal and transport connection;
-  Radiation monitoring system;

The systems of main cranes and small LLM are tested (16 small LLM have been tested so far).
Works on the internal and external lining have been completed.

MUFOP locking anchors are installed on the soffit structures of the West end wall.

The Arch ventilation system (installation of air ducts and ventilation equipment in the northern and southern ventilation centres, as well as in the process building).

Activities on the installation of the sealing membrane are underway.

Installation of cable boxes along the structures of the Arch external ladder.

 · Process building and auxiliary facilities:

- Process building (PB) - activities are carried out on arrangement of the facade of the eastern part of the building. Installation of cable ducts, cable laying.

Connection of 20 ton crane to the control panel. Installation of a fire alarm system. Installation of ventilation system air ducts. Activities on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal network pipelines, systems, metal structures. Installation of doors.

- Electrical Equipment Building - installation of fire alarm system, dismantling of transformers.
- Access Gateway for Fire Brigades - installation of internal networks pipelines, arrangement of external façade.
- Fire Extinguishing Pump Station – electric cable laying and installation of lighting system equipment.
- Sewage treatment facilities and pump station of storm water drainage - work on water level lowering and arrangement of the foundation. Installation of treatment facilities tanks.

Activities on arranging the NSC internal and external space are underway:

- Installation of pipelines for fire and industrial and potable water supply;
- Arrangement of the area of the southern gallery of hinged bearing in the turbine hall; delivery, assembling and installation of fire towers, installing the design fencing of the site from outside of the development wall, dismantling of the drainage gutter;
- Construction of roads and sidewalks in the local zone - 76%.