Within the NSC Project at the construction site the following works are being performed:
- Technological building and auxiliary facilities:
* Technological building (TB) — work is carried out on arrangement of the facade of the eastern part of the building. Installation of cable ducts, cable laying. Connection of 20 ton crane to the control panel. Installation of a fire alarm system. Installation of ventilation system air ducts. Work on grinding, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building. Installation of internal networks pipelines, systems, metal constructions. Installation of doors;
* Electrical Equipment Building (EEB) — installation of Fire Alarm System;
* Access Gateway for Fire brigades — installation of internal networks pipelines, installation of the equipment and doors;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors;
* Sewage treatment facilities and pump station of storm water drainage — work on water drainage and arrangement of the foundation. Installation of treatment facilities tanks.
- Works on arranging the NSC internal and external space:
* Installation of pipelines for fire and industrial and drinking water supply;
* Arrangement of the site of the southern galleries of hinged bearing near the turbine hall;
* Construction of roads in Local zone — 68%.
- Erection of Arch steelwork:
* Installation of the following main systems:
• Power supply system;
• Ventilation, gas purification and conditioning;
• Fire safety system;
• Water supply and sewerage system;
• Communication and industrial TV system;
• Physical protection and access control system;
• Integrated management and control system;
• System of internal and transport connection;
• Radiation monitoring system;
* Installation of MCS control panels in the central control panel. Connection of control panels to MCS. Works installation of small load-lifting mechanisms in the technological building are under way;
* Works on the internal and external lining are close to completion;
* Arch ventilation system (installation of air ducts and ventilation equipment in the northern and southern ventilation centres, as well as in the technological building);
* Preparation and installation of sealing anchors on the roof of the technological building and access lock for the fire brigades;
* Work on the installation of the sealing membrane are underway;
* Installation of cable boxes along the constructions of the Arch external ladder.