Within the NSC Project at the construction site the following works are being performed:
- Technological building and auxiliary facilities:
* Technological building (TB) — work on arrangement of the facade of the building eastern part, installation of cable ducts, cabling are underway. Preparation for crane beam installation for the 20 ton crane. Reassembly of 20 ton crane. Installation of Fire Alarm System. Works inside the building on polishing, coating, putty, painting of floors, walls and ceilings are underway. Installation of internal pipelines, systems, steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of Fire Alarm System. Installation of cable ducts, cable laying;
* Access Gateway for Fire brigades – installation of internal networks pipelines, installation of the equipment and doors;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors.
- Works on arranging the NSC internal and external space:
* Installation of fire fighting and drinking water pipelines;
* Construction of roads in Local zone — 53%.
- Erection of Arch steelwork:
* Installation of the following main systems:
• Power supply system;
• Ventilation, gas purification and conditioning;
• Fire safety system;
• Water supply and sewerage system;
• Communication and industrial TV system;
• Physical protection and access control system;
• Integrated management and control system;
• System of internal and transport connection;
• Radiation monitoring system;
* Contractor also performs installation of the MCS trolleys moving system in the northern garage. Work is underway to install the small lifting devices in the technological building;
* Completion of the works on exterior and interior facing;
* The work on hydraulic jacks and sliding ways dismantling is completed;
* Preparation for installation and installation of sealing anchors. Installation of the sealing membrane is underway.