Within the NSC Project at the construction site the following works are being performed:
- Technological building and auxiliary facilities:
* Technological building (TB) — work on arrangement of the facade of the building eastern part. Installation of cable ducts, cabling. Preparation for crane beam installation for the 20 ton crane. Reassembly of 20 ton crane. Installation of fire alarm system. Works inside the building on polishing, coating, putty, painting of floors, walls and ceilings. Installation of internal pipelines, systems, steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of fire-alarm system. Installation of cable trays, cable laying;
* Access Gateway for Fire brigades – installation of internal networks pipelines, systems, steel structures;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors.
- Works on arranging the NSC internal and external space:
* Arch end walls;
* Fire fighting water collection pool;
* Installation of fire fighting and drinking water pipelines;
* Arrangement of the thermal insulation of pipelines external engineering networks overpass;
* Construction of roads in Local zone — 39%.
- Erection of Arch steelwork:
* Installation of the following main systems:
• Power supply and equipment system;
• Ventilation gas purification and conditioning;
• Fire safety system;
• Water supply and sewerage system;
• Communication and industrial TV system;
• Physical protection and access control system;
• Integrated management and control system;
• System of internal and transport connection;
• Radiation monitoring system;
* Contractor also performs installation of the system of MCS trolleys movement in the northern garage;
* Arch facing is tested for leakage;
* Completion of the works on exterior and interior facing;
* Pre-assembly, assembly and preparation for sealing anchors installation.