NSC construction progress as of February 16, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

Technological building and auxiliary facilities:

Technological building (TB) — work on arrangement of the facade of the building eastern part. Installation of cable ducts, cabling. Preparation for crane beam installation for the 20 ton crane. Reassembly of 20 ton crane. Installation of fire alarm system. Works inside the building on polishing, coating, putty, painting of floors, walls and ceilings. Installation of internal pipelines, systems, steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of fire-alarm system. Installation of cable trays, cable laying;
* Access Gateway for Fire brigades – installation of internal networks pipelines, systems, steel structures.;
* Fire Extinguishing Pump Station — installation of fire pipelines, installation of doors.

Works on arranging the NSC internal and external space:

* Arch end walls;
* Walls of pivot mounting gallery;
* Fire fighting water collection pool;
* Installation of fire fighting and drinking water pipelines;
* Arrangement of the thermal insulation of pipelines external engineering networks overpass;
* Construction of roads in Local zone — 38%.

- Erection of Arch steelwork:

* Sealing anchors enlargement, preparation for assembly and installation;
* Installation of north garage shielding;
Preparation of northern (NVC) and southern (SVC) ventilation centers for installation of ventilation equipment. 
* Pipe laying, ventilation equipment installation in NVC and SVC;
* Arch facing preparation for leak test;
* Installation of the MCS trolleys movement system in the northern garage.