Within the NSC Project at the construction site the following works are being performed:
- Technological building and auxiliary facilities:
* Technological building (TB) — activities on installing a façade of east side of the building are being carried out. Installation of cable trays, cable laying. Preparation of 20-t crane for mounting. Installation of fire-alarm system. Works on polishing, pre-coating, coating, pouring, painting of floors, walls and ceilings inside the building are in progress. Pipe laying of internal circuits, systems, metal structures. Installation of doors;
* Electrical Equipment Building (EEB) — installation of fire-alarm system. Installation of cable trays, cable laying;
* Fire Units Access Lock (FSAL) — pipe laying of internal circuits, systems, metal structures. Sub-foundation works for sliding doors;
* Fire Extinguishing Pump Station — installation of pumping equipment and mounting of pumps.
- Works on arranging the NSC internal and external space:
* Installation of fire fighting and drinking water pipelines;
* Heat insulation of pipelines of external utilities rack;
* Construction of roads in Local zone — 36,6%.
- Erection of Arch steelwork:
* Pre-assembly works, pre-erection and erection of sealing anchors;
* Installation of north garage shielding;
* Preparation of northern (NVC) and southern (SVC) ventilation centers for installation of ventilation equipment.
* Pipe laying, ventilation equipment installation in NVC and SVC.