NSC construction progress as of January 19, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

Technological building and auxiliary facilities:

Technological building (TB) — works related to mounting the face of the eastern part of the building are underway. Works related to the installation of cable trunks, cable laying. Electrical installation works related to the installation of 20-ton crane. Installation of fire alarm system. Works related to polishing, pre-coating, coating, pouring and painting of floors, walls and ceilings inside the building. Installation of internal supply pipelines, systems and steel structures. Installation of doors;
* Electrical Equipment Building (EEB) — works related to installation of fire alarm system. Installation of cable trunks supports, cable laying;
* Fire Units Access Lock (FSAL) — installation of internal supply pipelines, systems, steel structures. Installation of the foundation base for sliding doors;
* Fire Extinguishing Pump Station — installation of foundations for pump equipment.

Works on arranging the NSC internal and external space:

* Installation of fire fighting and drinking water pipelines;
* Heat insulation of pipelines of external utilities rack;
* Construction of roads in Local zone — 36%.

- Erection of Arch steelwork:

* Pre-assembly and preparation of flashing anchors for installation;
Preparation of northern (NVC) and southern (SVC) ventilation centers for installation of ventilation equipment. Installation of ventilation equipment piping in NVC and SVC.