NSC construction progress as of January 12, 2017

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

Technological building and auxiliary facilities:

Technological building (TB) — works related to repair of concrete surfaces, polishing, pre-coating, coating and painting of walls and ceilings inside the building. Works on mounting of the building face are underway.

Activities on closing the tilting panel TP-2:

* Preparation of northern (NVC) and southern (SVC) ventilation centers for installation of ventilation equipment; 
* Installation of ventilation equipment piping in NVC and SVC.

Works on arranging the NSC internal and external space:

* Site cleanup, cleaning of passing routes;
* Reorganization of the Free Access Area (FAA) for a storage area for structures and equipment.

January 12, 2017
January 12, 2017
January 12, 2017
January 12, 2017
January 12, 2017
January 12, 2017