NSC construction progress as of December 22, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

Technological building and auxiliary facilities:

Technological building (TB) — works related to polishing, pre-coating, coating and painting of walls and ceilings inside the building. Installation of supports and fire-fighting water supply pipelines, doors;
* Electrical Equipment Building (EEB) — works related to installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems and steel structures.

Activities on closing the tilting panel TP-2:

* Installation of anchors of the west end wall;
* Pre-assembly and preparation of flashing anchors for installation;
* Preparation of northern (NVC) and southern (SVC) ventilation centers for installation of ventilation equipment. Installation of ventilation equipment piping in NVC and SVC.

Works on arranging the NSC internal and external space:

* Installation of fire fighting and drinking water pipelines;
* Heat insulation of pipelines of external utilities rack;
* Construction of roads in Local zone — 36%.

- Erection of Arch steelwork:

* Weight of Arch erected steelwork — 30,552 t;
* Works on moving the Arch into its design position are completed;
* Dismantling of the Arch sliding tracks in the Erection area.