Within the NSC Project at the construction site the following works are being performed:
- Technological building and auxiliary facilities:
* Technological building (TB) — works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building. Installation of supports and pipelines for fire water supply. The Contractor is installing the doors;
* Electrical Equipment Building (EEB) — installation of fire alarm systems and lighting within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems and metal structures.
- Works on arranging the NSC internal and external space:
* Outdoor cable routes (cable laying);
* Construction of roads in Local zone — 35%.
- Erection of Arch steelwork:
* Weight of Arch erected steelwork — 30,552 t;
* Works on moving the Arch into its design position are completed.