NSC construction progress as of November 17, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

 

- Main Cranes System (MCS) installation:

The Contractor completed the adjustment of MCS crane-runway girders;
The MCS tests were completed in the scope envisaged before the sliding.

Technological building and auxiliary facilities:

Technological building (TB) — works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building. Installation of supports and pipelines for fire water supply. The Contractor is installing doors. Mounting of the frame metal structures for the TB face heat insulation and lining is underway;
* Electrical Equipment Building (EEB) — installation of fire alarm systems and lighting within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures. Mounting of the frame metal structures for the EEB face heat insulation and lining is underway;

Works on arranging the NSC internal and external space:

* Outdoor cable routes (cable laying);
* Outdoor and underground utility systems (water supply, power supply, sewage system);
* Storm water catching basins;
* The Arch End walls;
* Construction of roads in Local zone — 34%.

- Erection of Arch steelwork:

* Weight of Arch erected steelwork — 30,552.99 t;
* The NSC ventilation stack is erected;
* Passes were installed at the Arch roof;
* Works on the installation of sealing anchors which were scheduled before the sliding are at the stage of completion;
* The Arch sliding works have been commenced on November 14, 2016.