NSC construction progress as of October 27, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of tertiary steel structures to the site;
- Installation of sliding system control module, inspection and installation of the Arch sliding equipment;
- Installation of anchors of East End wall;
- Installation of sealing anchors at the south-east and at the western end of Deaerator Stack and turbine hall;
- Installation of special doors of the Arch;
- Installation of protective shielding of Northern garage and runways;
- Completion of external and internal cladding installation; works on testing the sealing capacity of the cladding. Progress – 99 %;
- Ventilation system (installation of air ducts is near completion, works have been started on installing ventilation equipment);

- Main Cranes System (MCS) installation:

* adjustment of crane-runway girders and rails;
* alignment and connection of control panels to the MCS, testing of control systems;
* Preparation for MCS testing.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TEC) – works on polishing, priming, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures.  Progress (construction part) — 98.7%;
* Electrical Equipment Building (EEB) – installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures. Installation of framed steel structures for heat insulation of walls and facing of EEB facade;
* Fire Subdivisions Access Lock (FSAL) – polishing, priming, coating and painting of walls and ceilings inside the building;
* Fire water pumping station (FPS) – heat insulation of walls and facing of facade.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch End walls;
* Construction of roads in Local zone — 32%.

Erection of Arch western part steelwork:

Erected in total – 16,126.44 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

October 27, 2016
October 27, 2016
October 27, 2016
October 27, 2016
October 27, 2016
October 27, 2016