Within the NSC Project at the construction site the following works are being performed:
- delivery of tertiary steel structures to the site;
- mounting of sliding system control module, inspection and installation of the Arch sliding equipment;
- Installation of anchors of East End wall;
- installation of sealing anchors at the north-east;
- installation of special doors of the Arch;
- installation of protective shielding of North garage and runways;
- installation completion of external and internal cladding. Progress — 99%;
- ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress — 98%;
- erection of the NSC ventilation stack was completed.
- installation of sealing anchors.
- Main Cranes System (MCS) installation:
* adjustment of crane-runway girders and rails;
* alignment and connection of control panels to the MCS, testing of control systems;
* Testing of 25-t crane.
- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) — works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls from gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures. Progress (construction part) — 99.6%.
* Electrical Equipment Building (EEB) — installation of fire alarm system, and lighting system within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, steel structures. Installation of framed steel structures for heat insulation of walls and facing of EEB facade.
* Fire Units Access Lock (FSAL) — polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors. Installation of utilities inside the building.
* Fire pump station (FPS) — installation of southern fire water tank. Heat insulation and facing.
- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch End walls;
* Construction of roads in Local zone — 32%.
Erection of Arch western part steelwork:
Erected in total – 16,108.57 t
Erection of Arch eastern part steelwork:
Erected in total – 14,265.62 t