NSC construction progress as of October 6, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- delivery of tertiary steel structures to the site;
- mounting of sliding system control module, inspection and assembling of equipment for the Arch sliding;
- Installation of MPFOP anchors of East End wall; 
- installation of sealing anchors at the north-east; 
- installation of special doors of the Arch; 
- installation of protective shielding of North garage and runways;
- installation completion of external and internal cladding. Progress - 99%;
- ventilation system (preparation of air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparation of North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 98%;
- erection of the NSC ventilation stack was completed.

- Main Cranes System (MCS) installation:

* adjustment of crane-runway girders and rails;
* alignment and connection of control panels to the MCS, testing of control systems.

- Arrangement of technological building and auxiliary facilities:

* Technological building (TB) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls from gas blocks, roof sealing. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures.  Progress (construction part) - 99.6%.
* Electrical Equipment Building (EEB) – installation of fire alarm system and lighting within the EEB premises. Installation of supports, pipelines, re-bars, internal utilities, systems, metal structures. Mounting of the frame metal structures for the EEB face heat insulation and lining.  
* Fire Units Access Lock – polishing, pre-coating, coating and painting of walls and ceilings inside the building. 
* Fire pump station (FPS) –installation of the southern fire water tank. Arrangement of face heat insulation and lining.

- Arrangement of internal and external space of the NSC:

* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* the Arch end walls;
* Construction of roads in Local zone - 30%.

Erection of Arch western part steelwork:

Erected in total – 16,104.10 t

Erection of Arch eastern part steelwork:

Erected in total – 14,265.62 t

October 07, 2016
October 07, 2016
October 07, 2016
October 07, 2016
October 07, 2016
October 07, 2016