Within the NSC Project at the construction site the following works are being performed:
- Delivery of tertiary steel structures to the site;
- Mounting of sliding system control module, inspection and assembling of equipment for Arch sliding;
- installation of sealing membrane anchors along the end wall
- Installation of special doors of the Arch;
- Installation of sealing membrane of swing panels;
- Installation of protective shielding of North Garage;
- Pre-assembling and mounting of rolling doors of North Garage;
- Installation of external and internal casing. Progress - 99%;
- Ventilation system (preparing the air ducts for installation, installation of air ducts, installation of supports and scaffolding, preparing the North Ventilation Center (NVC) for installation of ventilation equipment). Progress - 91%;
- Welding of Arch Ventilation stack units. Pre-assembly of Ventilation stack maintenance sites.
- Main Cranes System (MCS) installation:
* Adjusting the crane beams and rails;
* Preparing the MCS bridges for rerolling to west side of the Arch;
* Adjusting and connecting MCS control panels.
- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – works relating to polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors, installation of dividing walls of gas blocks, roof sealing. Progress (construction part) - 98%;
* Electrical Equipment Building (EEB) – installation of fire alarm system within premises, mounting of cable supports and trays, installation of supports and pipes of fire-preventive and drinking water supply;
* Access gateway for fire brigades – roof sealing, polishing, pre-coating, coating and painting of walls and ceilings inside the building, installation of doors;
* Fire pump station (FPS) – works relating to pre-coating, coating and painting of walls inside the building;
* Site of diesel power plant for power supply – laying the electrical cables and connecting diesel generators, installation of equipment.
- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone - 28%.
Erection of Arch western part steelwork:
Erected in total – 16,019.88 t
Erection of Arch eastern part steelwork:
Erected in total – 14,265.62 t