Within the NSC Project at the construction site the following works are being performed:
- Delivery of steelwork to the site;
- Installation of protective shielding of Northern garage;
- Installation of special doors of the Arch;
- Installation of TP-5.1, TP-5.2, TP-6 tilting panels automatic jacks;
- Installation of control and instrumentation cable routes of Northern and Southern Ventilation Centres;
- Pre-assembly of monorail crane components in Southern Ventilation Centre;
- Pre-assembly and installation of access hole for MCS Northern garage (works completed);
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding. Overall progress – 95%;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports and scaffolding, preparation of NVC for vent systems installation. Air ducts installed – 86%;
- Installation of cable supports and cable ducts inside the Maintenance garage. Cable routing from NVC to Maintenance garage.
- Main Cranes System (MCS) installation:
* Leveling (alignment) of crane-runway girders;
* Cutting and installation of tracks.
- 25t crane for MCS Maintenance garage:
* Crane components have been delivered to the Assembly site;
* Final leveling of crane-runway girders and installation of tracks.
- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – walling and roofing (reinforcement, formwork, concreting). Overall progress (construction part) – 91.5%;
* Electrical Equipment Building (EEB) – installation of cable supports, cable trays, and staircase. Overall progress (construction part) – 100%;
* Fire Subdivision Access Lock (FSAL) – construction works completed. Finishing of the premise is underway. Overall progress (construction part) – 100%;
* Firewater pumping station (FWR) – roofing (installation of scaffolding and formwork). Overall progress (construction part) – 99%. Reinforcement works for foundations for tanks.
- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.
Erection of Arch western part steelwork:
Erected in total – 15,827.45 t
Erection of Arch eastern part steelwork:
Erected in total – 14,265.62 t