NSC construction progress as of June 9, 2016

Select another date

Within the NSC Project at the construction site the following works are being performed:

- Delivery of steelwork to the site;
- Installation of Northern garage floor grating (tertiary structures);
- Installation of special doors of the Arch;
- Installation of TP-5.1, TP-5.2, TP-6 tilting panels automatic jacks;
- Installation of stairs between Western wall walkways;
- Pre-assembly and installation of access hole for MCS Northern garage;
- Installation of purlins of internal and external cladding;
- Installation of external and internal cladding;
- Ventilation system (preparation of air ducts for installation, installation of air ducts, supports, and scaffolding, preparation of NVC for vent systems installation and connection with air ducts).
- Installation of cable supports and cable ducts inside the Maintenance garage. Laying of cable from NVC to Maintenance garage. 

- Main Cranes System (MCS) installation:
* Final leveling (alignment) of crane-runway girders;
* Cutting and installation of tracks. 

- 25t crane for MCS Maintenance garage:
* Crane components have been delivered to the Assembly site; the equipment is undergoing incoming control.

- Arrangement of technological building and auxiliary facilities:
* Technological building (TEC) – installation of reinforcing cages and formwork of TEC walls, heat insulation of roof, primer coating and puttying of walls and ceilings. Overall progress (construction part) – 91 %;
* Electrical Equipment Building (EEB) – installation of cable supports and cable trays, cable routing, and heat insulation of roof. Overall progress (construction part) – 91 %;
* Fire Subdivision Access Lock (FSAL) – heat insulation of roof. Installation of scaffolding, formwork, and reinforcing of the northern floor slab area. Overall progress (construction part) – 88%;
* Firewater pumping station (FWR) – installation of formwork of northern tank foundation; works commenced on reinforcing the foundation for southern tank. Overall progress (construction part) – 99%;
* Diesel power plant area – laying of electrical cables and connection of diesel generators.

- Arrangement of internal and external space of the NSC:
* Outdoor cable routes;
* Outdoor and underground utility systems;
* Storm water catching basins;
* Construction of roads in Local zone.

Erection of Arch western part steelwork: 

Erected in total – 15,793.33 t

Erection of Arch eastern part steelwork: 

Erected in total – 14,265.62 t

June 09, 2016
June 09, 2016
June 09, 2016
June 09, 2016
June 09, 2016
June 09, 2016