NSC construction progress as of July 30, 2015

Select the another date

Within the NSC Project at the construction site the following works are being performed:
- Pre-assembling and installation of Western end wall gangways;
- Installation and tightening of bolts at the junction area of West and East halfs of the Arch
- Completing and assembly of cladding purlines;
- Preliminary erection and assembly of steel plating packages for cladding, as well as laying of heat insulating material, assembly of EPDM membrane, assembly of bearing clip and Kalzip panels;
- Assembly of scaffolding and preparation of air ducts for assembling, assembly of air ducts of the Arch ventilation system;
- Installation of Main Cranes System elements (west bridge, classic carriage, secure carriage)

- Arrangement of technological building and auxiliary facilities:
* Technological building (TB) – walling, roofing and arranging the building columns (assembly of fittings and formwork, concreting, concrete curing);
* Electrical device building – roofing (preparatory works, assembly of fittings and formwork);
* Fire units acces airlock (concrete curing).

- Arrangement of external and internal space of NSC (northern side):
* Storm and fire extinguishing water catchment basins;
* Arch end walls
* Outdoor underground services.

Assembly of metal structures of Western half of the Arch:

Metal structures assembled in total – 14,554.3 tons

Assembly of metal structures of Eastern half of the Arch:

Metal structures assembled in total –  14,109.268 tons

Joining of West an East halfs of the Arch was completed on July 24, 2015. Bolt tightening is in process.  

July 30, 2015
July 30, 2015
July 30, 2015
July 30, 2015
July 30, 2015
July 30, 2015